we are upgrading from 10.5 to 10.11 side-by-side I have a question related to DB Migration?
Is your question related to the free trial, or to a production (customer) instance?
No
What are you trying to achieve? Please describe it in detail.
I need to understand the order of steps while migrating DB from 10.5 to 10.11 (side-by-side)
- Request DBA new schemas for 10.11 for JDBC pools and MWS Schema
- execute DB configurator on 10.11 and create new tables for new schemas
- Install 10.11 servers on new Schemas (for IS and MWS)
- request DBA to import and export data from 10.5 to 10.11 and verify New server.
Can you please clarify this order is correct ? Please suggest if any activity is missing.