new Mobile Task

Hi All! I’ve installed all the mobile from software AG Installer 9.8. I’ve already created a process with a task implemented. but when i right click on my task, the “Create new Mobile Task right click on the task” option doesnt shows up, do I need to do something more?

Thanks in advance!!!


Hi,

it seems you have everything installed properly. Can you please try the following:

  • open perspective “Mobile Development”
  • open menu “File” => “New” => “Other” => “Mobile Task Integration”
  • in the wizard: is the Task you’ve created shown there?

Regards,
Michael

Hi Mike! thanks for the answer. It’s all ok now, I had to uninstall my designer and delete all his files in the computer, reinstall everything again and that did the trick,

Thanks!!!

Hi,

I’m glad to hear that it works now!

Regards,
Michael