Migration checklist

Hi All,

Good day to you.

We are planning a data center migration activity in which we have to take care of webMethods suit. This is just a robo copy of existing environment so no changes in the existing configurations and other stuff.

I just want to know the basic check list for this activity and also need the order in which we have to stop and start the below wM components.

Components we have : IS ( clustered ) , Broker Server , CentraSite Server , MWS , Optimize , Mediator server , Enterprise Gateway & SQL DB.

Hope this will be done during an official MDT, I would suggest to first block the incoming traffic going into your ESB and then follow the sequences below:

Enterprise Gateway, CentraSite Server, Mediator server, Optimize, Broker Server, MWS , IS ( clustered )