migrating process models from 8.0 to 9.5

Hi All,

I have some basic doubts regarding the 9.5 upgrade process,

Is it possible to migrate the IS packages and process models from 8.0 to 9.5 directly or should i first migrate to 8.2 then followed by the migration from 8.2 to 9.5

Thanks.
Ganesh

There is direct upgrade supported from 80 to 9.5 from Software AG. Please see the 9.5 upgrade guide present here: http://techcommunity.softwareag.com/ecosystem/documentation/webmethods/wmsuites/wmsuite9-5_sp1/SysReqs_Installation_and_Upgrade/9-5_Upgrading_webMethods_Products.pdf

Hi Ganesh,

For the IS packages, You can use Deployer to extract the packages from old to new envt. For BPM process, you can export the old process and import them in the latest Designer ad then publish it directly to the new version.

For more detailed info, refer to chapter 10 of webMethods 95 upgrade guide.

Hi,

please note that Deployer usually does not allow deployment across versions, esp. when the first number is changing.

Regards,
Holger

Hi Holger,

Thanks for pointing out.

You can in this case, export the Deployer build from older version and then import them in the newer version of Deployer.