Task started and completed

Dear all.

I have the following problem: I have a simple process with a task. The task gets called, data is correctly transfered, then a user works with the task and commits the form. No errors, but the process is not executing from this point on. Problem is that the task’s status is set to “Started” in the Process Instance view, but opening the tasks shows that it’s status is “Completed”. So on the one hand I have a started task in the process, on the other hand i have a completed task. Can someone help me?

Thanks in advance

Henning

do you get any error message in your IS or MWS logs ??

Regards,
Rajesh

Hi

I am encountering the same problem.Any solution.