Hi,
Is there any body know how to schedule the Integration Components . So that I can give the trigger as time rather than any resource operation /document .
this is for to perform some batch operation on specific times
thanks & regards
Hi,
Is there any body know how to schedule the Integration Components . So that I can give the trigger as time rather than any resource operation /document .
this is for to perform some batch operation on specific times
thanks & regards
I don’t think it is possible murali.
Murali, there was a thread on this topic not too long ago. Check out [url=“wmusers.com”]wmusers.com.
I just posted a solution for this. It involves a configured operation for a custom adapter. Check out the post:
SOLUTION: Configured operation needs to know enable-disable